This Week’s Activities:

  • Completed haul-off of topsoil stockpile
  • Removed existing utilities
  • Completed rough grade excavation for parking garage and south parking lot
  • Continued fill and compaction activities at central site
  • Began digging building pad

Next Week’s Activities:

  • Continuing fill and compaction
  • Continuing digging building pads

 