This Week’s Activities:

  • Electrical/com/gas/duct bank installation
  • Grading activities for building pads ongoing
  • Spoil haul-off ongoing

Next Week’s Activities:

  • Continue duct bank installation
  • Excavate and install site lighting
  • Excavate and install storm sewer piping and junction boxes
  • Continue spoil haul-off
  • Excavate and grade the two remaining pads