This week’s activities:

  • Completed sanitary and domestic utility tie-in at Alamo St.
  • Placed mud slabs at building A and C
  • Started to form the foundation to building A
  • Continued to remove pier spoils
  • Waterproofed elevator pit in building C and E
  • removed trees east of future parking garage
  • Installed conduit under mud slab in building E
  • Worked on temp power at north end of site

Next week:

  • Continue forming building A foundation
  • Placing building E mud slab
  • Placing sidewalk at Alamo Street utility tie-ins
  • Sanitary utility at north end of site
  • Continue to deliver form work material
  • Continue to haul off excavated soil
  • Install new fence where trees were removed east of parking garage

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s