This

week’s activities:

  • Continue forming building A foundation
  • Started installing reinforcing at building A foundation
  • Continue to haul spoils offsite
  • Started underground fire line installation
  • Installed new fence at east side of future parking garage
  • Working on temp power at north end site
  • Plumbing and electrical layout for building A

Next week:

  • Complete the forming of building A foundation
  • Continue installing reinforcing in building A foundation
  • Complete fire line installation
  • Continue to haul off excavated soil
  • Continue plumbing and electrical layout for building A

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s