This Week’s Activities:

  • concrete pour at building D area
  • base placement on parking garage pad
  • setting collars and connections to existing storm
  • excavation and installation of site lighting raceway
  • building B backfill and perimeter drain installation
  • building E formwork and rebar
  • wrecking building B and C

Next Week’s Activities:

  • wrecking building D
  • formwork and rebar building E
  • backfill and perimeter drain building B and C