This week’s activities:

  • Placing concrete for A1 casting bed
  • Base placement on parking garage pad
  • Asphalt in Cunningham St.
  • Excavation and installation of site lighting raceway
  • Building B/C below grade waterproofing
  • Building E concrete placement
  • Formwork and concrete for pier caps B/C

Next week’s activities:

  • Wrecking building D formwork
  • Parking garage retaining wall footings
  • Parking garage pier drilling
  • Tilt wall formwork and casting bed grading