This week’s update:

  • Place building C tiltwall panels
  • Continue grade beams and pier caps in parking garage
  • Form and place south wall footing
  • Start steel erection in building A
  • Continue forming TW columns for B/C

Next week’s activities:

  • Erect building B tiltwall panels
  • Place grade beams on north end building B/C
  • Continue excavation and installation of the storm sewer
  • Place south retaining wall footing in PG
  • Continue erecting steel and decking on building A