This week’s activities:

  • Erect TW panels for building “B”
  • Continue the erection of the structural steel for building “A”
  • Form and place north patio grade beams
  • Crawl space MEP rough-in and temp power
  • Continue forming panels for building “D”

Next week’s activities:

  • Continue steel erection and decking for building “A”
  • Start erecting steel for building “B”
  • Place TW panels in building “D”
  • Start layout and forms for building “E” TW panels
  • Complete grade beams in parking garage