DSO Buiding Update: May 21 – 25, 2018

This Week's Activities: Place Level 3 Concrete Building A Continue Framing Building A Ramp backfill Overhead rough in Building A Roof steel Building A Next Week's Activities: Continue Roof steel at Building A Elevator Pit concrete pour at Garage Metal Decking at Building B MEP Rough - in Building A Generator Housekeeping Pads

DSO Building Update: April 30 – May 4, 2018

This week's activities: Detailing Sequence 2 steel Decking and detailing for sequence 1-2 CMU wall construction at CEP Excavation for elevator pit South retaining wall formwork Next Week's Activities: Erection of tilt columns at Building C Placement of Building D2 casting slab Erection of Sequence 4 Beams and columns A/D bridge Crawlspace MEP