DSO Building Update: April 30 – May 4, 2018

This week's activities: Detailing Sequence 2 steel Decking and detailing for sequence 1-2 CMU wall construction at CEP Excavation for elevator pit South retaining wall formwork Next Week's Activities: Erection of tilt columns at Building C Placement of Building D2 casting slab Erection of Sequence 4 Beams and columns A/D bridge Crawlspace MEP