This week’s activities:
- Detailing Sequence 2 steel
- Decking and detailing for sequence 1-2
- CMU wall construction at CEP
- Excavation for elevator pit
- South retaining wall formwork
Next Week’s Activities:
- Erection of tilt columns at Building C
- Placement of Building D2 casting slab
- Erection of Sequence 4
- Beams and columns A/D bridge
- Crawlspace MEP