DSO Building Update: May 28 – June 1, 2018

This week's activities: Steel Decking Building B Continue Framing Building A South Retaining wall backfill at Garage Continue Overhead rough in Building A Concrete at Elevator Pit Next week's activities: Equipment pads level 2 Building A Framing Level 2 Building A Continue Metal Decking at Building B MEP Rough in Building A Mechanical Equipment arrival