This week’s activities:

  • Steel Decking Building B
  • Continue Framing Building A
  • South Retaining wall backfill at Garage
  • Continue Overhead rough in Building A
  • Concrete at Elevator Pit

Next week’s activities:

  • Equipment pads level 2 Building A
  • Framing Level 2 Building A
  • Continue Metal Decking at Building B
  • MEP Rough in Building A
  • Mechanical Equipment arrival