This week’s activities:

Building A Level 1 Restroom Floor Tile
Building A Ceiling Cloud Framing
Building A Level 2 Data Room Finish Floor
Building A Level 3 Exterior Wall Framing
Building D Level 1 Window Store Front Framing
Building E Level 2 Ducts
North Parking Lot Limestone
Next week’s activities:

Building B Paint
Building C Level 3 Duct
Building D Level 2 Window Glass
Building E Level 1 Store Front Framing

 