This week’s activities:

  • Building A Level 2 Flooring
  • Building A Level 3 Restroom Tile
  • Building B/C Store Front Frame and Glass
  • Building C Level 1 Low Walls
  • Building D Level 3 Ducts
  • Building E Mechanical Room
  • Parking Garage Elevator

Next week’s activities:

  • Building C Level 3 Exterior Panels
  • Building E Level 3 Store Front Glass
  • Building D Level 2 Furred Down
  • Parking Garage Concrete Pour