DSO Building Update: December 31, 2018 – January 4, 2019

This week’s activities:

  • Building C Level 2 Light Fixtures
  • Curbs at North Parking Lot
  • Light fixtures Building B level 1
  • Exterior metal panels Building C
  • Ceiling grid Building D Level 1
  • LED light fixtures Bridge B/C

Next week’s activities:

  • Continue grading for Amphitheater
  • Continue Building D Level 3 DIRTT Walls
  • Continue Building D Level 2 Light Fixtures
  • Continue metal panels under bridges