This week’s activities:

  • Limestone south Bldg. A
  • Wood slats at Elevators
  • Light poles
  • Turf at amphitheater
  • Structural steel for louver enclosures
  • Formwork and rebar for sidewalks

Next week’s activities:

  • Continue sidewalks at north and west of building
  • Continue grading for sidewalks thru the building
  • Continue louvers enclosures at cooling tower
  • Continue entrance mats throughout the building