This week’s activities:

  • Limestone west bldg. D.
  • Irrigation north of building.
  • Light poles at south parking lot.
  • Landscaping west building D.
  • Louver enclosures at dumpster gate.
  • Formwork and rebar for pathways.

Next week’s activities:

  • Continue sidewalks at north and south of building.
  • Continue grading for sidewalks thru the building.
  • Continue louver enclosures at condensing units.
  • Continue limestone retaining wall.

 