DSO Building Update: December 3-6, 2018

This week's activities: Building A level 3 Kitchenette Building A west exterior light fixtures Building A level 3 DIRTT wall panels Building D & E Bridge wall framing Building B & C Bridge wood at TV stand Grading for Amphitheater West sidewalk formwork Next week's activities: Continue grading for Amphitheater Continue Building B Level 2 … Continue reading DSO Building Update: December 3-6, 2018