DSO Building Update: March 4-8, 2019

This week's activities: Limestone south Bldg. A Wood slats at Elevators Light poles Turf at amphitheater Structural steel for louver enclosures Formwork and rebar for sidewalks Next week's activities: Continue sidewalks at north and west of building Continue grading for sidewalks thru the building Continue louvers enclosures at cooling tower Continue entrance mats throughout the … Continue reading DSO Building Update: March 4-8, 2019

DSO Building Update: February 25, 2019- March 1, 2019

This week's activities: Asphalt north entrance Wood slats at Boardroom DIRTT wall panels bldg. B level 3 Limestone amphitheater Ceiling tile bldg. D level 1 Formwork and rebar for walkway paths Next week's activities: Continue sidewalks at north of building Continue Bldg. B/C Level 3 DIRTT wall panels Continue ceiling tile Bldg. E Level 2 … Continue reading DSO Building Update: February 25, 2019- March 1, 2019

DSO Building Update: February 18-22, 2019

This week's activities: Asphalt north entrance Wood slats at Boardroom DIRTT wall panels bldg. B level 3. Limestone amphitheater Ceiling tile bldg. D level 1 Formwork and rebar for walkway paths. Next week's activities: Continue asphalt south entrance Continue Bldg. B/C Level 3 DIRTT wall panels Continue ceiling tile Bldg. E Level 2 Continue limestone … Continue reading DSO Building Update: February 18-22, 2019