DSO Building Update: February 12-16, 2018

This week's activities: Placing concrete for A1 casting bed Base placement on parking garage pad Asphalt in Cunningham St. Excavation and installation of site lighting raceway Building B/C below grade waterproofing Building E concrete placement Formwork and concrete for pier caps B/C Next week's activities: Wrecking building D formwork Parking garage retaining wall footings Parking … Continue reading DSO Building Update: February 12-16, 2018

Building Update: Feburary 5-9, 2018

This Week's Activities: concrete pour at building D area base placement on parking garage pad setting collars and connections to existing storm excavation and installation of site lighting raceway building B backfill and perimeter drain installation building E formwork and rebar wrecking building B and C Next Week's Activities: wrecking building D formwork and rebar … Continue reading Building Update: Feburary 5-9, 2018