DSO Building Update: April 2-6, 2018

This week's activities: Erect the building A tiltwall panels Continue forming tiltwall panels for building C Grade beams and pier caps in parking garage Tiltwall rough-in for MEP system Re-open N. Alamo St. at Cunningham St. Excavate for south retaining wall at parking garage Next week's activities: Place building C tiltwall panels Continue grade beams … Continue reading DSO Building Update: April 2-6, 2018