Blog

DSO Building Update: July 16-20, 2018

This week's activities: Concrete Slab Building "D" Level 2 Building "E" Concrete Steel Reinforcement Building "B" Curtain Wall Framing Building "B" Glulam Beams Parking Garage Concrete Steel Reinforcement Insulation in Cross Space  Building "A" Building "A" Level 2 Wall and Door Framing Next week's activities: Continue installing Window Glass Building "B" Continue installing Glulam Beams … Continue reading DSO Building Update: July 16-20, 2018