DSO Building Update: February 19-23, 2018

This week's activities: Wrecking Building D formwork. Parking garage retaining wall footings. Parking garage pier drilling. Tilt wall formwork and casting bed grading. Tilt wall mockup. Next week's activities: Continuing pier drilling. Setting form and Rebar at retaining wall. Connection of storm line. Permanent relocation of power. New CPS pole. Continuing tilt wall formwork and … Continue reading DSO Building Update: February 19-23, 2018

Building Update: Feburary 5-9, 2018

This Week's Activities: concrete pour at building D area base placement on parking garage pad setting collars and connections to existing storm excavation and installation of site lighting raceway building B backfill and perimeter drain installation building E formwork and rebar wrecking building B and C Next Week's Activities: wrecking building D formwork and rebar … Continue reading Building Update: Feburary 5-9, 2018