DSO Building Update: December 24-28, 2018

This week's activities: Building C Level 2 light fixtures Building A Level 3 cabinets Cable Tray Building D level 3 Countertops Building C level 2 Ceiling Grid Building C level 1 Exterior Metal Stairs Building A Next week's activities: Continue grading for Amphitheater Continue Building D Level 3 DIRTT Walls Continue Buiding D Level 2 … Continue reading DSO Building Update: December 24-28, 2018

DSO Building Update: June 4-8, 2018

This Week's Activities: Steel Bridge Building "A/B" Framing Level 2 Building "A" Precast Erection at Parking Garage Continue Overhead rough in Building "A" Metal Decking Level 3 Building "B" Next Week's Activities: Steel Connections between Building "B/C" Continue Framing Level 2 Building "A" Continue Metal Decking at Building "B" Continue MEP Rough - in Building … Continue reading DSO Building Update: June 4-8, 2018